Main Title Assessment of Dam Safety Coal Combustion Surface Impoundments (Task 3) Final Report. PacifiCorp, Naughton Power Station, Kemmerer, Wyoming.
CORP Author Clough, Harbour and Associates, Albany, NY.; Lockheed Martin Services Inc., Edison, NJ.; Environmental Protection Agency, Washington, DC.
Year Published 2009
Report Number CHA-NO-20085-2020-1510
Stock Number PB2010-106785
Additional Subjects Electric power production plants ; Dam safety ; Coal wastes ; Surface impoundments ; Waste management ; Site assessment ; Dikes ; Embankments ; Operations ; PacifiCorp Naughton Power Station ; Kemmerer(Wyoming) ; Coal combustion surface impoundments
Holdings
Library Call Number Additional Info Location Last
Modified
Checkout
Status
NTIS  PB2010-106785 Some EPA libraries have a fiche copy filed under the call number shown. 07/26/2022
Collation 152p
Abstract
CHA was contracted by Lockheed Martin (a contractor to the United State Environmental Protection Agency) to perform site assessments of selected coal combustion surface impoundments (Project No. 0-381 Coal Combustion Surface Ipoundments/Dam Safety Inspections). As part of this contract, CHA was assigned to perform a site assessment of PacifiCorp's Naughton Power Station, which is located in Kemmerer (Lincoln County), Wyoming as shown on Figure 1--Project Location Map. CHA made a site visit on September 9 and 10, 2009 to inventory coal combustion surface impoundments at the facility, to perform visual observations of the containment dikes, and to collect relevant information regarding the site assessment.