AMERICAN CREOSOTE SITE CASE STUDY: SOLIDIFICATION/STABILIZATION OF DIOXINS, PCP, AND CREOSOTE FOR $64 PER CUBIC YARD

Citation:

Bates*, E R., F. Akindele*, AND D. Sprinkle. AMERICAN CREOSOTE SITE CASE STUDY: SOLIDIFICATION/STABILIZATION OF DIOXINS, PCP, AND CREOSOTE FOR $64 PER CUBIC YARD. Environmental Progress & Sustainable Energy. American Society of Chemical Engineering (AIChE), New York, NY, 21(2):79-84, (2002).

Description:

This case study describes the development of solidification/stabilization (S/S) formulas and their application to rededicate the American Creosote site in Jackson, Tennessee. During 1998 and 1999, 45,000 cubic yards of soil contaminated with Creosote, PCP, and Dioxins were treated using S/S at a total cost of $64 per cubic yard. Formulations, design, specifications, and costs are presented.