Skip common site navigation and headers
United States Environmental Protection Agency
National Pollutant Discharge Elimination System (NPDES)
Begin Hierarchical Links EPA Home > OW Home > OWM Home > NPDES Home > Stormwater > Menu of BMPs End Hierarchical Links
Menu of BMPs Home
 
BMP Background
 
Public Education & Outreach on
Stormwater Impacts
 
Public Involvement/
Participation
 
Illicit Discharge Detection & Elimination
 
Construction Site Stormwater Runoff Control
 
Post-Construction Stormwater Management in New Development & Redevelopment
 
Pollution Prevention/Good Housekeeping for Municipal Operations
 
Stormwater Home
 
 
 

 

 
Search BMPs

Filter by Minimum Measure
GO Browse Fact Sheets Search Help

Land Grading

Minimum Measure: Construction Site Stormwater Runoff Control

Subcategory: Construction Site Planning and Management

Photo description: Soils exposed from land grading activities

Description

Land grading involves reshaping the ground surface to planned grades as determined by an engineering survey, evaluation, and layout. Land grading provides more suitable topography for buildings, facilities, and other land uses and helps to control surface runoff, soil erosion, and sedimentation during and after construction.

Applicability

Land grading is applicable to sites with uneven or steep topography or easily erodible soils, because it stabilizes slopes and decreases runoff velocity. Grading activities should maintain existing drainage patterns as much as possible.

Siting and Design Considerations

Before grading activities begin, a construction site operator must make decisions regarding the steepness of cut-and-fill slopes and how the slopes will be

  • Protected from runoff
  • Stabilized
  • Maintained

Prepare a grading plan that establishes which areas of the site will be graded, how drainage patterns will be directed, and how runoff velocities will affect receiving waters. Also in the grading plan, include information about when earthwork will start and stop, establish the degree and length of finished slopes, and dictate where and how excess material will be disposed of (or where borrow materials will be obtained if needed). Land grading should be a key consideration for Construction Sequencing. Try to minimize exposed soils at any given time during construction. Incorporate in the plan any berms, diversions, and other stormwater practices that require excavation and filling.

Care should be taken if blasting agents or explosives are used. These products may contain perchlorates, which are water soluble chemicals. If explosives containing perchlorate must be used, then good housekeeping practices should be employed to ensure that any debris is properly disposed.

A low-impact development BMP that a site operator can incorporate into a grading plan is site fingerprinting, which involves clearing and grading only those areas necessary for building activities and equipment traffic. Maintaining undisturbed temporary or permanent buffer zones in the grading operation provides a low-cost sediment control measure that will help reduce runoff and offsite sedimentation. Let the lowest elevation of the site remain undisturbed to provide a protected stormwater outlet before storm drains or other construction outlets are installed.

Limitations

Improper grading practices that disrupt natural stormwater patterns might lead to poor drainage, high-runoff velocities, and increased peak flows during storm events. Clearing and grading the entire site without vegetated buffers promotes offsite transport of sediments and other pollutants. Design the grading plan with erosion and sediment control and stormwater management goals in mind; to ensure that the plan is implemented as intended, carefully supervise grading crews.

Maintenance Considerations

Check all graded areas and supporting erosion and sediment control practices periodically, especially after heavy rainfalls. Promptly remove all sediment from diversions or other stormwater conveyances, and if washouts or breaks occur, repair them immediately. To prevent small-scale eroded areas from becoming significant gullies, maintain them promptly.

Effectiveness

Land grading is an effective way to reduce steep slopes and stabilize highly erodible soils when properly implemented with stormwater management and erosion and sediment control practices. Land grading is not effective when drainage patterns are altered or when vegetated areas on the perimeter of the site are destroyed (USEPA, 2004).

Cost Considerations

Land grading is practiced at virtually all construction sites. It can take a certified engineer or landscape architect several hours of work to incorporate stormwater and erosion and sediment controls in the grading plan. It might take extra time to excavate diversions and construct berms. Also, fill materials might be needed to build up low-lying areas or fill depressions. Where grading is performed to manage on-site stormwater, the cost of fine grading, soil treatment, and grassing is approximately $2 per square yard of earth surface area and shallow excavation/trenching (1 to 4 feet deep) with a backhoe in areas not requiring dewatering can be performed for $4 to $5 per cubic yard of removed material (R. S. Means, 2000). Larger scale grading requires a site-specific assessment of an alternative grading apparatus and a detailed fill/excavation material balance to retain as much soil on site as possible.

References

R. S. Means, 2000. Heavy Construction Cost Data. 14th Annual Edition. Kingston, MA.

State of Delaware. No date. Delaware Erosion and Sediment Control Handbook for Development. Department of Natural Resources and Environmental Control, Division of Water Conservation.

State of North Carolina. 1988. Erosion and Sediment Control Planning and Design Manual. North Carolina Sedimentation Control Commission and North Carolina Department of Natural Resources and Community Development, Raleigh, NC.

USEPA (U.S. Environmental Protection Agency). 1992. Stormwater Management for Industrial Activities: Developing Pollution Prevention Plans and Best Management Practices. U.S. Environmental Protection Agency, Office of Water, Washington, DC.

USEPA (U.S. Environmental Protection Agency). 1993. Guidance Specifying Management Measures for Sources of Nonpoint Pollution in Coastal Waters. EPA 840-B-92-002. U.S. Environmental Protection Agency, Office of Water, Washington, DC.

USEPA (U.S. Environmental Protection Agency). 2004. Development Document for Final Action for Effluent Guidelines and Standards for the Construction and Development Category. EPA-821-B-04-001. Washington, DC.

 

Office of Water | Office of Wastewater Management | Disclaimer | Search EPA

Begin Site Footer

EPA Home | Privacy and Security Notice | Contact Us

Last updated on May 24, 2006
URL:http://cfpub.epa.gov/npdes/stormwater/menuofbmps/index.cfm