1,4-Dioxane (inhalation) Assessment Milestones and Dates
Milestone Projected Start Date * Projected End Date *
Draft Development (hazard identification) FY10/3rd Quarter FY10/3rd Quarter
Release lit search and evidence tables FY10/3rd Quarter FY10/3rd Quarter
Draft Development (dose-response analysis) FY10/3rd Quarter FY11/2nd Quarter
Agency Review FY11/2nd Quarter FY11/3rd Quarter
Interagency Science Consultation FY11/3rd Quarter FY11/4th Quarter
Public Comment Period FY11/4th Quarter FY11/4th Quarter
External Peer Review FY11/4th Quarter FY13/3rd Quarter
Final Agency Review/Interagency Science Discussion and Posting Final Assessment FY13/3rd Quarter FY13/4th Quarter
* For EPA, the Fiscal Year (FY) starts in October and ends in September of the following year. First quarter runs from October through December; the second from January through March; the third from April through June; and the fourth from July through September.