Mirex Assessment Milestones and Dates
Milestone Projected Start Date * Projected End Date *
Release problem formulation materials FY01/2nd Quarter FY07/1st Quarter
Public meeting TBD ** TBD **
Release literature search & evidence tables TBD ** TBD **
Public Meeting TBD ** TBD **
Agency Review FY07/1st Quarter FY07/4th Quarter
Interagency Science Consultation FY07/4th Quarter FY08/1st Quarter
Release public comment draft FY08/1st Quarter FY10/3rd Quarter
Public meeting TBD ** TBD **
Release peer review draft TBD ** TBD **
Peer review meeting TBD ** TBD **
Revise assessment TBD ** TBD **
Interagency Science Discussion FY10/3rd Quarter FY12/1st Quarter
Post final assessment TBD ** TBD **
* For EPA, the Fiscal Year (FY) starts in October and ends in September of the following year. First quarter runs from October through December; the second from January through March; the third from April through June; and the fourth from July through September.

** To be determined.