Milestone Projected Start Date * Projected End Date *
Draft Development (hazard identification) FY01/2nd Quarter FY07/1st Quarter
Release lit search and evidence tables TBD ** TBD **
Draft Development (dose-response analysis) TBD ** TBD **
Agency Review FY07/1st Quarter FY07/4th Quarter
Interagency Science Consultation FY07/4th Quarter FY08/1st Quarter
Public Comment Period FY08/1st Quarter FY10/3rd Quarter
External Peer Review TBD ** TBD **
Final Agency Review/Interagency Science Discussion and Posting Final Assessment FY10/3rd Quarter FY12/1st Quarter
* For EPA, the Fiscal Year (FY) starts in October and ends in September of the following year. First quarter runs from October through December; the second from January through March; the third from April through June; and the fourth from July through September.

** To be determined.

Recent Additions | Advanced Search | IRIS Home | Environmental Assessment | Research


Local Navigation


Jump to main content.